Time | Item | Owner(s) | Notes |
---|
| Administrative | | |
5min | Review Deadlines | | Upcoming Deadlines - Sprint 10 begins 9/6/2017
- Sept. 1st finish prototypes and final design
- Waiting on final ADC choice - Choice made, Daniel proceeding forward with it.
- Focus on PCB for small sensors, give Allison info to order by COB 9/6/2017
- Then work on ADC for large sensors once all components for small sensors have been ordered
- Goal is to get STEM students building small sensors at the beginning of October, large sensors beginning of November
- July-Mid. Sept., purchasing for devices
- Oct. through Nov. begin build process of devices with ULL/David Thibodaux students
- About 10 boxes to be ready in the next few days - Krulick, Daniel (CGI Federal) is working on it.
- These will be deployed at LDEQ (to be be calibrated , compared to the regulatory sensors)
|
| O&M | | Status update: - We need to start thinking when and where we would deploy our next sensor prototypes, and what sensors those prototypes will include.
- Next prototype sensors will be deployed at USGS site
- Comeaux, Justin M (CGI Federal) tested out current and new algorithms for the O3 sensor, MQ131.
- Matkin, Benjamin K (CGI Federal)- Prioritizing bamboo build for Dashboard this sprint before further features. This will improve deployment time.
|
| Hardware | | Status update: - Hardware status:
- Alphasense higher quality PM sensors, 5 ordered
- Probably will have to write driver
- new analog to digital converter for big boxes
- 5v Fans ordered
- Custom PCB
- Finishing PCB components in Eagle
- Small board super close to done
|
| Firmware and device management | | |
| API | | Status update: - LEARN-187: Clean up code for OSS release, pt. 2
- LEARN-188: Setup Bamboo CI for Kinota API code.
- In progress, should complete by Fri. Sept. 8
- Will be doing OSS release to GitHub on Monday Sept. 11 (in coordination with OGC working group meeting)
- LEARN-189: MQTT Architecture
|
| Visualization and Use Cases | | |
| Architecture & Analytics | Chepudira, Karthik (CGI Federal) | Targeting for 9/5/2017 - Sprint 9 - AQI POC - Completed
- As per initial discussion, an API to derive AQI Hourly index (8 hour) will be developed as a a derived product on top of Sensor things api
- The API will also allow pulling of historical AQI data
- Initial design will focus on standing up of an MVP to facilitate integration into dashboard.
- Having a working version of the AQI will facilitate a focus group meeting to engage SME's for best practice discussion of AQI design
- Simulation of 240 sensors on dev dashboard - Currently in progress
|
| Outreach | | Status update:
- GitHub integration with Confluence
- Content links need to be filtered/removed/rewritten
- Add page to show AgileIQ to GitHub Bridge (A2GB) history
|
| Review Scrum Board | | |
| | | |