Time | Item | Owner(s) | Notes |
---|
| Administrative | | |
5min | Review Deadlines | | Upcoming Deadlines - Sprint completion 6/14/2017
- July 21st finish prototypes and final design
- Early August, purchasing for devices
- Early September begin build process of devices with ULL students
|
| O&M | | Status update: - LEaRN Wordpress site
- We need to start thinking when and where we would deploy our next prototypes, and what sensors those prototypes will include.
- SSL Certificate/ Custom domain practices via Azure
- Matkin, Benjamin K (CGI Federal) started Unify 360 ticket to acquire permissions for SSL Certificate use in Azure
- Custom Domain through Azure provides domain name and www.
- Need to architect subdomain plan for purchasing WildCard certificate.
- Custom domains can be purchased through Azure and assigned SSL Cert. Matkin, Benjamin K (CGI Federal) has clear path forward.
|
| Hardware | | Status update: - Mobile sensor plans (Alghamdi, Taghreed (LEARN))
- meeting and rough outline done
- Hardware status:
- Low-cost PM sensors, 4 ordered from DF Robot
- Basic Communication done, making more robust
- Aeroqual higher quality O3 sensors, 6 total ordered
- Received - not yet communicating
- Alphasense higher quality PM sensors, 5 ordered
- Received - not yet communicating
- Temperature/Humidity/Pressure sensor
- Successfully receiving data
- Case
- Working with Allison to contact already established contacts
- Inventory Management
|
| Firmware and device management | | |
| API | | Status update: - LEARN-137: Service-driven paging
- Complete. Awaiting code review.
- LEARN-105: Pass through informative error messages from SensorThings REST API
- Complete. Awaiting code review.
|
| Visualization and Use Cases | | Status update: - Ridgeway, Terysa (CGI) reached out to Carlee to schedule a visit to review data/data sets that are available
- Using the Thingsboard.io application as a basis for dashboard prototyping
- Awaiting traffic data from LCG - current LA DOTD data is only done annually, or every 3-5 years
- Can also talk with Monique Boulet at the MPO
- Use cases:
- Added details to use cases
- Began wire framing/prototypes of dashboards to support specific use cases.
- Will e-mail LCG re. data access tomorrow/Wed.
- Visualization
- LEaRN website
- We need to develop, by July 1st, a LEaRN website, hosted on Azure, that serves as a landing page to the project
- Need to register a domain name
- Set up a web server is Azure
- Add content from proposal as a project description section.
- Links to:
- Dashboard
- Source code
- Agile IQ
- etc.
- Matkin, Benjamin K (CGI Federal) will work on this for the next sprint
- Dev Dashboard site was live http://learndash-st.com/ (taken offline to avoid charges)
- Custom domain purchased through Azure (refunded after canceling)
- Decide the Domain names for the web end points ( Dev, API etc) Miles, Brian (CGI Federal) & Matkin, Benjamin K (CGI Federal)
|
| Architecture | Chepudira, Karthik (CGI Federal) | - Virtual Sensor (Azure IoT integrated) still working and available on the dashboard
- Integration of Azure App service (API) with the Cassandra cluster complete.
|
| Review Scrum Board | | |