2017-08-28 LEaRN Status Meeting (CGI)

Original CGI Document

gt

SubjectStatus Meeting (CGI)
Project NameLEaRN
Meeting DateAugust 28, 2017
Chairperson
Dial-in Info

Host key: 199735


Join WebEx meeting<https://cgifederal.webex.com/cgifederal/j.php?MTID=m4a162804d9845bdfd1947806438d109a>
Meeting number: 747 675 789
Meeting password: g26tiUHP

Join by phone
Call-in toll-free number: 1-866-5573330 (US)
Call-in number: 1-443-8637759 (US)
Show global numbers<https://www.tcconline.com/offSite/OffSiteController.jpf?cc=6573812350>
Leader PIN: 1146
Conference Code: 657 381 2350

Can't join the meeting? Contact support.<https://cgifederal.webex.com/cgifederal/mc>

IMPORTANT NOTICE: Please note that this WebEx service allows audio and other information sent during the session to be recorded, which may be discoverable in a legal matter. You should inform all meeting attendees prior to recording if you intend to record the meeting.

Time / Location2017-08-21 2:00 PM CST

 

 

Discussion Items

TimeItemOwner(s)Notes
Administrative
5minReview Deadlines 
  • Upcoming Deadlines

    • Sprint 9 begins 8/22/2017
    • Sept. 1st finish prototypes and final design
      • Waiting on final ADC choice - Choice made, Daniel proceeding forward with it.
    • July-Early Sept., purchasing for devices
    • Oct. through Nov. begin build process of devices with ULL/David Thibodaux students
    • About 10 boxes to be ready in the next few days - Krulick, Daniel (CGI Federal) is working on it.
      • These will be deployed at LDEQ (to be be calibrated , compared to the regulatory sensors)
 O&M

Status update:

 Hardware

Status update:

  • Hardware status:
    • Alphasense higher quality PM sensors, 5 ordered
      • Communicating, but not sure if correctly
    • new analog to digital converter for big boxes
      • arrived
      • ADS1015 way too small to hand-solder - will need mini prefab board
        • 2 mm x 1.5 mm x 0.4 mm
    • 5v Fans ordered
      • should arrive anyday now
    • Custom PCB
      • Finishing PCB components in Eagle
        • delayed - finishing now
 Firmware and device management

Status update:

  • Ticket, LEARN-196 will be mostly completed since we don't have demos this week.
 API

Status update:

  • LEARN-148: Clean up code for OSS release
    • Complete
  • LEARN-187: Clean up code for OSS release, pt. 2
    • Complete. Waiting for code review.
 Visualization and Use Cases

Status update:

  Architecture & AnalyticsChepudira, Karthik (CGI Federal) 

Targeting for 9/5/2017 - Sprint 9

  • AQI POC
    • As per initial discussion, an API to derive AQI Hourly index (8 hour) will be developed as a a derived product on top of Sensor things api
    • The API will also allow pulling of historical AQI data
    • Initial design will focus on standing up of an MVP to facilitate integration into dashboard.
    • Having a working version of the AQI will facilitate a focus group meeting to engage SME's for best practice discussion of AQI design
  • Simulation of 240 sensors on dev dashboard - TBD
 Outreach
  • GitHub integration with Confluence
    • Flat HTML page output finished
      • Resources are downloaded and saved and will be able to access from GitHub Pages
      • Content links need to be filtered/removed/rewritten
        • Links to resources need to be made relative
      • Dynamic menus filtering for GitHub Pages is finished
      • Experiment with styles tag to allow custom styling
    • Then will automate using a cron job running on a VM hosting a Drupal instance
      • This Drupal instance may be running as part of AgileIQ infrastructure
    • Molinski, Samuel J (CGI Federal) has a prototype of JIRA integration.
      • HERE: https://github.com/LafayetteEngagementAndResearchNetwork/AirChallenge/issues
      • The team needs to review and mark any tickets that should not be migrated. To do so, label as follows:
        • 'Project Risk', 'Project Action Item', 'Project Issue', 'Non Public', 'nonPublic', 'github-ignore'.  If there is any sensitive issues I would recommend added on of them.  Also if there is any other labels I should add to the black list, I can add that if needed.
    • Plan to enable Confluence and JIRA integration by Sept. 7th
  • GitHub integration with source code
    • Code will be pushed from Bitbucket to GitHub manually for releases as appropriate
 Review Scrum Board 
    

 

 

Decisions

DescriptionOwner(s)
  

Action items

Date Assigned 

DescriptionOwner(s)

Due Date

Completion Date Notes 
 
  •  
      

Risks and Issues

Risk or Issue

Date Identified 

 

DescriptionOwner(s)Follow-up DateNotes 
  
  •  Notes for this item